In CPM, if a delay occurs on a non-critical activity, what is a possible consequence?

Prepare for the Heavy Civil Exam 2. Study with comprehensive flashcards and multiple-choice questions, complete with hints and explanations. Enhance your readiness and confidence!

Multiple Choice

In CPM, if a delay occurs on a non-critical activity, what is a possible consequence?

Explanation:
In CPM scheduling, every activity has float (slack) that shows how long it can be delayed without delaying the project finish. A delay on a non-critical activity uses up its float, and if that float is exhausted, the activity becomes critical, meaning any further delay will push the project completion date later. So a delay on a non-critical activity could extend the project duration if its float is consumed and it shifts into the critical path. It doesn’t automatically shorten the project, and it isn’t guaranteed to affect the duration unless the float is used up.

In CPM scheduling, every activity has float (slack) that shows how long it can be delayed without delaying the project finish. A delay on a non-critical activity uses up its float, and if that float is exhausted, the activity becomes critical, meaning any further delay will push the project completion date later. So a delay on a non-critical activity could extend the project duration if its float is consumed and it shifts into the critical path. It doesn’t automatically shorten the project, and it isn’t guaranteed to affect the duration unless the float is used up.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy